
Recent court decisions have signaled the courts’ proclivity to prefer arbitration over full-fledged litigation when provisions in construction contracts are called into question. While the courts recognize a party’s constitutional right to a jury trial, the courts also lean strongly towards resolving disputes via arbitration as a matter of public policy, especially if a construction contract carves out arbitration as an alternative to litigation.
In Avr Davis Raleigh v. Triangle Constr. Co., 818 S.E.2d 184 (N.C. App. 2018), the North Carolina Appeals Court reviewed the issue of whether the contracting parties selected binding arbitration as an alternative to litigation. The contract at issue was an AIA A201-2007 form document. Under the terms of the contract, the parties elected to arbitrate claims under $500,000 but to litigate claims over this amount. However, if there were several claims under $500,000 but the aggregate of all claims exceeded $500,000, then the contract implied that all claims would be arbitrated. Since the claims involved were an amalgamation of the two, the contracting parties disagreed about whether the arbitration provision would apply. The plaintiff interpreted this provision to mean litigation was mandatory when at least one claim exceeded $500,000 and that arbitration was mandatory when no single claim exceeded this amount. In contrast, the defendant interpreted this provision as meaning that when there were several claims worth less than $500,000 individually, but more than $500,000 aggregately, then all claims must be arbitrated. The trial court agreed with the plaintiff’s interpretation.
In overruling the trial court, the North Carolina Court of Appeals deferred to North Carolina’s strong public policy in favor of resolving disputes via arbitration. The Court of Appeals recognized there were several reasonable interpretations of the provision at issue, including both interpretations articulated by the plaintiff and defendant. However, when faced with “doubts concerning the scope of arbitrable issues,” the Court of Appeals held that the trial court should have deferred to arbitrating the claims rather than litigating them since the interpretation favoring arbitration falls more squarely within North Carolina’s public policy on the subject.
The United States District Court for the Southern District of Maryland also addressed the interpretation of an arbitration provision in a construction contract in Matrix N. Am. Constr., Inc. v. SNC Lavalin Construction, Inc., 2018 U.S. Dist. LEXIS 130434 (D. Md.). Here, the parties disagreed over whether the contract’s “dispute resolution section” mandated arbitration when all attempts at resolution failed or whether arbitration was merely permissive under these circumstances. The plaintiff argued that the terms of the contract set forth a three-step dispute resolution process, with the first step being negotiation, the second step being mediation and the third step being litigation. According to the plaintiff, once the parties satisfied steps one and two, litigation was the only remaining option.
In reviewing the contract, the District Court noted that the contract did not define the terms “dispute mitigation” or “dispute resolution procedures.” However, once submitted to dispute resolution, the contract stated that the dispute may be settled by a single arbitrator whose decision would be binding on the parties. This section of the contract did not provide for any alternate methods of resolution, such as mediation. The plaintiff argued that arbitration was permissive because the contract’s language noted that all disputes not settled “may be referred to arbitration.” The District Court disagreed and held that arbitration was mandatory under the contract and not at all permissive.
In determining that arbitration was obligatory and not permissive under these circumstances, the Matrix court looked to the Fourth Circuit’s interpretation of the word “may” in this context. The Fourth Circuit saw the word “may” as used here as implying that the aggrieved party could either choose to arbitrate or choose to abandon its claim. If courts were to adopt the plaintiff’s permissive view of arbitration, then doing so would render the contract provision as being meaningless and would always make the decision to arbitrate a voluntary one. In other words, there would be no need to include a mandatory arbitration provision in a contract if the choice to arbitrate was always voluntary and not required. Using this analysis, the Matrix court held that the decision to arbitrate was mandatory; the only other alternative would be the plaintiff’s abandonment of its claim.
What these cases highlight is the courts’ proclivity to have parties arbitrate a claim when a construction contract’s language is ambiguous, in doubt, or open to multiple interpretations. From a subrogation perspective, practitioners always need to be aware of a construction contract’s language and how that language will impact how claims advance and what remedies are available. Litigation may not always be the first and best option.
Recent Posts
Categories
- Products Liability
- CPSC Recalls
- Construction Defects
- Statute of Limitations-Repose
- Minnesota
- California
- Experts – Daubert
- Maryland
- Jurisdiction
- CPSC Warning
- Rhode Island
- Experts - Reliability
- Podcast
- Anti-Subrogation Rule
- Workers' Compensation
- Uncategorized
- Negligence
- New York
- Contracts
- Cargo - Transportation
- Landlord-Tenant
- Sutton Doctrine
- Waiver of Subrogation
- Arbitration
- Texas
- Pennsylvania
- AIA Contracts
- Evidence
- Florida
- Economic Loss Rule
- Malpractice
- Wyoming
- Spoliation
- Tennessee
- Water Loss
- Indiana
- Michigan
- Comparative-Contributory Negligence
- Contribution-Apportionment
- Assignment
- Missouri
- Parties
- Public Policy
- Civil Procedure
- New Jersey
- Res Judicata
- Arkansas
- Damages
- Damages – Personal Property
- Product Liability
- Arizona
- Certificate of Merit
- Litigation
- West Virginia
- Oklahoma
- Builder's Risk
- Contractual Subrogation
- Equitable Subrogation
- Georgia
- Illinois
- Insurable Interest
- Limitation of Liability
- Mississippi
- Made Whole
- Delaware
- Settlement
- Subrogation – Equitable
- Construction
- Premises Liability
- Joint or Several Liability
- Montana
- Duty
- Privity
- New Mexico
- Right to Repair Act
- Massachusetts
- Landlord
- Tenant
- Building Code
- Causation
- Architects-Engineers
Tags
- Subrogation
- Products Liability
- Construction Defects
- Product Liability
- Podcast
- Minnesota
- California
- Subro Sessions
- Experts
- Jurisdiction
- Maryland
- Texas
- Statute of Repose
- Jurisdiction - Personal
- Statute of Limitations - Accrual
- Experts – Daubert
- Waiver of Subrogation
- Rhode Island
- CPSC Recalls; Products Liability
- Contracts
- Negligence
- Civil Procedure
- Landlord-Tenant
- Experts - Reliability
- Pennsylvania
- Georgia
- Certificate of Merit
- Louisiana
- Amazon-eBay
- Made Whole
- Economic Loss Doctrine
- New York
- Florida
- Construction Contracts
- Anti-Subrogation Rule
- Illinois
- Experts – Qualifications
- New Jersey
- Parties
- Ohio
- Right to Repair Act
- Statute of Limitations - Tolling
- Contracts - Enforcement
- Arizona
- Sutton Doctrine
- West Virginia
- Indiana
- Design Defect
- Spoliation
- Water Damage
- Evidence
- Evidence - Hearsay
- Connecticut
- Damages
- Privity
- Condominiums
- Massachusetts
- Tennessee
- Statute of Limitations
- workers' compensation subrogation
- Limitation of Liability
- Apportionment
- Expert Qualifications
- Exculpatory Clause
- Amazon
- Arbitration
- Negligence – Duty
- Wisconsin
- Workers’ Compensation
- Public Policy
- Missouri
- Negligent Undertaking
- Statute of Limitations - Contractual
- Delaware
- Loss of Use
- Vehicles
- Indemnification
- Architects-Engineers
- Washington
- AIA Contract
- Warranty - Implied
- Res Judicata
- Settlement
- Statute of Limitations - Repose
- Improvement
- Michigan
- Malpractice
- Idaho
- Internet Sales
- Non-Party at Fault
- Spoliation – Fire Scene
- Gross Negligence
- Malfunction Theory; Design Defect
- Mississippi
- Statute of Limitations – Discovery Rule
- Independent Duty
- Cargo-Transportation
- Contribution
- Implied Warranty of Habitability
- Warranty - Construction
- North Carolina
- Utah
- Standing
- Comparative Fault
- Circumstantial Evidence
- Res Ipsa
- New Mexico
- Contracts - Formation
- Unconscionable
- Failure to Warn
- Manufacturing Defect
- Pleading
- Removal
- Entire Controversy Doctrine
- Motion to Intervene
- Subrogation; High-Net-Worth; Damages; Art; Cargo-Transportation; Anti-Subrogation Rule
- Nevada
- Virginia
- Products Liability – Risk-Utility
- Lithium-ion battery
- Burden of Proof
- Anti-Subrogation Rule; Wyoming; Landlord-Tenant; Sutton Doctrine
- New Hampshire
- Oklahoma
- Sanctions
- Builder’s Risk
- Contractual Subrogation
- Equitable Subrogation
- Insurable Interest
- Joint-Tortfeasors
- Arkansas
- Kentucky
- Daubert
- Fire - Cigarettes
- Colorado
- Causation
- Third Party
- Discovery-Sanctions
- Accepted Work
- Malfunction Theory
- Montana
- Independent Contractor
- Privilege
- Betterment
- Damages-Code Upgrades
- Insurance Coverage
- First Party Claims
- Forum-Venue
- Warranty – Express
- AIA Contracts
- Anti-Indemnity Statutes
- Products Liability - Foreseeability
- Discovery - Experts
- MCS-90
- Substantial Completion
- Reimbursement
- Assignment
- Counterclaim
- Products Liability; Malfunction Theory
- Economic Loss Rule
- Unfair Trade Practices
- Evidence – Probative Value
- Parties – Real Party in Interest
- Status of Repose
- Evidence - Public
- Construction Defects - Fixtures
- Subrogation – Equitable
- Additional Insured
- Trespass
- Contract
- COVID-19
- Incorporation by Reference
- Damages – Emotional Distress
- Oregon
- Third Party Spoliation
- No-Fault Subrogation
- Products Liability; Mississippi
- Inverse Condemnation
- Jury Instructions
- Food and Beverage
- South Carolina
- California Court of Appeals Holds Subrogating Carrier Cannot Assert Claims of Its Suspended Insured
- Debt Collection
- Medical Benefits
- Montreal Convention
- Immunity
- Products Li
- Wyoming
- Release
- Liens
- Kansas
Authors
Archives
- March 2025
- February 2025
- January 2025
- December 2024
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
- December 2023
- November 2023
- October 2023
- September 2023
- August 2023
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- November 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- January 2020
- December 2019
- November 2019
- October 2019
- September 2019
- August 2019
- July 2019
- June 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- December 2018
- November 2018
- October 2018
- September 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- March 2018
- February 2018
- January 2018
- December 2017
- November 2017
- October 2017
- September 2017
- August 2017
- July 2017
- June 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017
- December 2016
- November 2016
- October 2016
- September 2016
- August 2016
- July 2016
- June 2016
- May 2016
- April 2016
- March 2016
- February 2016
- January 2016
- December 2015
- November 2015
- October 2015
- September 2015
- August 2015
- July 2015
- June 2015
- February 2015
- January 2015
- November 2014
- October 2014
- September 2014
- May 2014
- April 2014
- December 2013
- August 2013
- May 2013
- February 2013